440 Washington Street Case Study
440 Washington Street is a 12 story, 60,000 sq. ft. ground-up building project started by First Standard on August 1, 2017. The original expected completion date was May, 2019, however, First Standard was able to complete the foundation and framing three months ahead of schedule, and the remainder of the project is expected to continue at an elevated pace, moving up the completion date to early January, 2019. The new residential building will contain 50 units and retail shops on the first floor. Additionally, the building’s amenities include a full service gym, laundry, parking garage, bike storage, and large common room and terrace on the 2nd floor.





Foundation started August 1st, 2017

Last foundation concrete pour February 27th, 2018

Superstructure started March, 2018

Topping out May 2nd, 2018

Scaffolding coming down October 5th, 2018