440 Washington Street Case Study

440 Washington Street is a 12 story, 60,000 sq. ft. ground-up building project started by First Standard on August 1, 2017. The original expected completion date was May, 2019, however, First Standard was able to complete the foundation and framing three months ahead of schedule, and the remainder of the project is expected to continue at an elevated pace,   moving up the completion date to early January, 2019.  The new residential building will contain 50 units and retail shops on the first floor. Additionally, the building’s amenities include a full service gym, laundry, parking garage, bike storage, and large common room and terrace on the 2nd floor.

weightlifting.png
washing-machine.png
car-in-a-garage.png
bicycle.png
terrace.png

Foundation started August 1st, 2017 

Image-29.jpeg

Last foundation concrete pour February 27th, 2018

unnamed.jpg

Superstructure started March, 2018

unnamed-1.jpg

Topping out May 2nd, 2018

unnamed-2.jpg

Scaffolding coming down October 5th, 2018

unnamed-3.jpg

In all that we do, one thing remains constant:

WE ARE THE MASTER BUILDERS OF THE 21 ST CENTURY.

bottom of page